POTENTIAL PROJECTS
Project Reference - 19053592
Project Tiltle
Replacement of 42” Flare Line at GCs 03,04,06,07,08 and Drain Sump Vent Line at GCs 03,04,06,07,08 & 21
Client
Kuwait Oil
Company
Location
Kuwait
Start Date
12/6/2019
End Date
29/12/2019
Project Reference - 6600033834
Project Tiltle
Upgrade Control System at Uthmaniyah and
Hawiyah GOSPs
Client
Saudi Aramco
Location
Udhailiyah - KSA
Start Date
30/11/2014
End Date
30/06/2019
Project Reference - CA/PD/3570
Project Tiltle
Engineering, Procurement & Construction Of Modernization Of Obsolete Instrumentation Project(Moip) MAA Refinery
Client
Kuwait National Petroleum Company
Location
Kuwait
Start Date
6/10/2006
End Date
12/31/2012
Project Reference - 6510693609
Project Tiltle
WCM & BS&W Analyzers Preventive
Maintenance & Repair
Client
Saudi Aramco
Location
SGPD - KSA
Start Date
30/11/2014
End Date
29/11/2021
Project Reference - 6510874187
Project Tiltle
Supply & Install Communication
Shelters at Four Sites
Client
Saudi Aramco
Location
Abha/Jizan - KSA
Start Date
1/5/2018
End Date
30/09/2019
Project Reference - 6510890866
Project Tiltle
Smart Positioners Upgrade in Abqaiq
Oil Plants
Client
Saudi Aramco
Location
Abqaiq
Start Date
10/6/2018
End Date
10/10/2019
Project Reference - HQ365IS15
Project Tiltle
Maintenance of Fire & Gas
Detection System
Client
Al Khafji Joint Operations
Location
Khafji
Start Date
2/10/2017
End Date
1/10/2020
Project Reference - HQ422SS16
Project Tiltle
Maintenance, Servicing, and Overhauling of
Actuated Control Valves
Client
Al Khafji Joint Operations
Location
Khafji
Start Date
5/12/2018
End Date
4/10/2019
Project Reference - 1128296
Project Tiltle
Bottom Tank Cathodic Protectioon Works - Civil Activities
Client
Saipem
Location
Kuwait
Start Date
5/12/2018
End Date
30/04/2019
Project Reference - 14051353
Project Tiltle
Operation & Maintenance of Bulk Chemical Facilities and Effluent Water Disposal Plants in Company Areas
Client
Kuwait Oil
Company
Location
Kuwait
Start Date
15/11/2014
End Date
14/11/2019
Project Reference - 15051363
Project Tiltle
Condition Monitoring & Preventive Maintenance Services of Production Facilties in SEK Areas.
Client
Kuwait Oil Company
Location
Kuwait
Start Date
1/12/2015
End Date
30/11/2020
Project Reference - 6600033620
Project Tiltle
Base Crew Manpower & Equipment
at RTPD
Client
Saudi Aramco
Location
Rastanura - KSA
Start Date
15/09/2013
End Date
31/07/2021
Project Reference - ME/MC/5248/2018
Project Tiltle
Base Crew Manpower & Equipment
at RTPD
Client
Saudi Aramco
Location
Kuwait
Start Date
5/12/2017
End Date
4/12/2022
Project Reference - 13050755
Project Tiltle
Supply,Installation&Maintenance of scada system
at North kuwait Field Instrument / RTU panel /
Scada for 157 ESP wells
Client
KOC/BAKER HUGHES
Location
Kuwait
Start Date
14/09/2014
End Date
17/03/2021
Project Reference - 6798-Z-3170-001
Project Tiltle
E&I Construction Works At Mina
Al Ahmadi Refinery
Client
KNPC/SKEC
Location
Kuwait
Start Date
16/06/2015
End Date
31/07/2019
Project Reference - SCR-2037
Project Tiltle
Well Head Maintenance & Services for 70 Jurassic Wells in North Kuwait
Client
KNPC/L&T
Location
Kuwait
Start Date
1/5/2018
End Date
31/08/2019
Project Reference - 0115/SC/AG/0019
Project Tiltle
Electrical & Instrumentation Shutdown Works For Replacement of Old & Obsolete Substation M20 at MAA Refinery Project
Client
KNPC/L&T
Location
Kuwait
Start Date
1/5/2018
End Date
31/12/2018
Project Reference - 4500002586
Project Tiltle
Bolt Torqing & Tensioning and
other services
Client
EQUATE
Location
Kuwait
Start Date
20/06/2013
End Date
31/10/2018
Project Reference - 4025/2K7
Project Tiltle
Installation of new air assisted flare stacks at gc-16, 17, 27 & 28
Client
Kuwait Oil Company
Location
Kuwait
Start Date
20/06/2007
End Date
19/06/2010
Project Reference - 46762
Project Tiltle
First Potable Water Pipeline Network for
West Kuwait
Client
Kuwait Oil Company
Location
Kuwait
Start Date
20/03/2011
End Date
10/10/2013
Project Reference - 27070
Project Tiltle
New 52" LP and 42" HP Fuel Gas Lines from Shuaiba M/F (M/F SH01) to M/F "X" in Burgan
Client
Kuwait Oil Company
Location
Kuwait
Start Date
2/6/2005
End Date
1/6/2008
Project Reference - 6510916360
Project Tiltle
Maintain SGPD Wells ESD and
Hydraulic Panels
Client
Saudi Aramco
Location
SGPD - KSA
Start Date
20/06/2019
End Date
19/06/2022
Project Reference - HQ422SS16
Project Tiltle
Modification of LP Separator Bridle
Flushing System
Client
Al Khafji Joint Operations
Location
Khafji
Start Date
25/6/2019
End Date
22/12/2019
Project Reference - 6510895100
Project Tiltle
Revalidation and Mothballing of SAGPD Gas
Flowlines and Trunklines
Client
Saudi Aramco
Location
SGPD - KSA
Start Date
18/10/2018
End Date
1/11/2021
Project Reference - 3000809606-2
Project Tiltle
Calibrate / Certify Beamex
Equipment
Client
Saudi Aramco
Location
Shedgum
Start Date
17/10/2018
End Date
16/11/2018
ON-GOING PROJECTS
CONSTRUCTION PROJECTS - No.6510874187
Project Tiltle
Provide Communication Shelters at
Four Sites
Client
Saudi Aramco
Client Contact
Abdulrahman Saad Al-Otaibi +966-13-880-0030
Value "SAR"
5150000
Location
Abha - Jizan
Duration
01/05/2018 to 30/09/2019
Duration
Ongoing
CONSTRUCTION PROJECTS - No.510900009
Project Tiltle
Installation of Air Compressor at Uthmaniyah Water Supply Plant
Client
Saudi Aramco
Client Contact
Bohorah Qassim
Value "SAR"
610000
Location
Udhailiyah
Duration
16/12/2018 to 15/04/2019
Duration
Ongoing
CONSTRUCTION PROJECTS - No.6510890866
Project Tiltle
Smart Positioners Upgrade in
Abqaiq Oil Plants
Client
Saudi Aramco
Client Contact
Emad S. Al Harbi
Value "SAR"
2403270
Location
Abqaiq
Duration
10/06/2018 to 10/10/2019
Duration
Ongoing
CONSTRUCTION PROJECTS - No.6510897215
Project Tiltle
Installation and Commissioning of Nitrogen Generator Units at UGOSP-04 and UGOSP-13
Client
Saudi Aramco
Client Contact
Moahmmed Al Hinde
Value "SAR"
3650000
Location
Uthmaniyah
Duration
01/12/2018 to 31/07/2019
Duration
Ongoing
CONSTRUCTION PROJECTS - No.6510895821
Project Tiltle
Electrical & Instrumentation connection for HAWTAH-831
Client
Saudi Aramco
Client Contact
Santhosh Kumar
013 577-0959
Value "SAR"
4625000
Location
Hawtah
Duration
01/12/2018 to 30/11/2019
Duration
Ongoing
CONSTRUCTION PROJECTS - No.4300190647
Project Tiltle
Replace Defected MV Cable
at Jubail Ar-Razi Plant
Client
Sabic
Client Contact
Kazeem Saleh
Value "SAR"
511500
Location
Jubail
Duration
21/03/2018 to 18/17/2019
Duration
Ongoing
CONSTRUCTION PROJECTS - No.6510924868
Project Tiltle
Troubleshoot & Repair Back-up Diesel Generator Panel
Client
Saudi Aramco
Client Contact
Julio Naranjo Mola
+966 14 397-8576
Value "SAR"
127000
Location
Shedgum
Duration
23/6/2019 to 22/9/2019
Duration
Ongoing
CONSTRUCTION PROJECTS - No.6510928322
Project Tiltle
SWID Fire Detection Systems Upgrade at QSWP
Client
Saudi Aramco
Client Contact
Value "SAR"
893000
Location
Qurayyah
Duration
8/1/2019 to 05/31/2020
Duration
Ongoing
CONSTRUCTION PROJECTS - No.6510926154
Project Tiltle
Flange Face Machining
for UGP
Client
Saudi Aramco
Client Contact
Meshaal M. Al-Nuaim
013 576-6569
Value "SAR"
603100
Location
Uthmaniyah
Duration
08/08/19 to 04/07/2022
Duration
Ongoing
CONSTRUCTION PROJECTS - No.6510929551
Project Tiltle
UGP TOOL/MACHINES
REPAIRS
Client
Saudi Aramco
Client Contact
Nuaim Meeshal
Value "SAR"
837000
Location
Uthmaniyah
Duration
22/08/19 to 01/08/2022
Duration
PO Yet to be Placed
MAINTENANCE PROJECTS - No.6600033620
Project Tiltle
Base Crew Manpower &
Equipment
Client
Saudi Aramco
Client Contact
Ibrahim Al Khaldi
'0504987355
Value "SAR"
75,962,488
Location
Ras Tanura
Duration
01/11/2014 to 31/10/2020
Duration
Ongoing
MAINTENANCE PROJECTS - HQ422SS16 (011163)
Project Tiltle
Maintenance, Servicing, and Overhauling of Actuated Control Valves
Client
Al Khafji Joint Operations
Client Contact
Mohamd K. Alam
013 765 6726
Value "SAR"
5658594
Location
Khafji
Duration
05/12/2018 to 04/05/2019
Duration
Ongoing
MAINTENANCE PROJECTS - 6510876730
Project Tiltle
Preventive Maintenance for Ventil Relief Valve Test Benches
Client
Saudi Aramco
Client Contact
Ibrahim Al Kulaib
Value "SAR"
1416000
Location
Udhailiyah
Duration
01/07/2018 to 30/06/2021
Duration
Ongoing
MAINTENANCE PROJECTS - 6510887023
Project Tiltle
Red-Eye WCM & BS&W Analyzers Preventive Maintenance & Repair
Client
Saudi Aramco
Client Contact
Ibrahim Al Kulaib
Value "SAR"
17025000
Location
S. Ghawar Producing
Duration
05/09/2018 to 26/08/2021
Duration
Ongoing
MAINTENANCE PROJECTS - HQ365IS15
Project Tiltle
Maintenance of Fire &
Gas Detection System
Client
Al Khafji Joint Operations
Client Contact
Abdullah Mufeh al Qahtani
Value "SAR"
7360000
Location
Khafji
Duration
11/02/2017 to 11/01/2020
Duration
Ongoing
MAINTENANCE PROJECTS - 6510895100
Project Tiltle
Revalidation and Mothballing of SAGPD Gas Flowlines and Trunklines
Client
Saudi Aramco
Client Contact
Hamzah A. Al-Khateeb
Tel: +966 13 5776583
Value "SAR"
11856000
Location
SAGPD
Duration
18/10/2018 to 01/11/2021
Duration
Ongoing
MAINTENANCE PROJECTS - 6510908612
Project Tiltle
Maintenance Services for
Analyzer at QSWP
Client
Saudi Aramco
Client Contact
Value "SAR"
2706000
Location
Qurayyah
Duration
25/03/2019 to 02/03/2022
Duration
Ongoing
MAINTENANCE PROJECTS - 6510916360
Project Tiltle
Maintain SGPD Wells ESD and Hydraulic Panels
Client
Saudi Aramco
Client Contact
Omar Al-Sadhan
+966 3 577-7543
Value "SAR"
8474149
Location
SGPD
Duration
20/6/2019to
19/6/2022
Duration
Ongoing
MAINTENANCE PROJECTS - HQ422SS16 ( 011398 )
Project Tiltle
Replacement of Motor on the Skid of Water Injection for Pump P-573B
Client
Al Khafji Joint Operations
Client Contact
Mohamd K. Alam
013 765 6726
Value "SAR"
1732500
Location
Khafji
Duration
25/06/2019 to 01/10/2019
Duration
Ongoing
MAINTENANCE PROJECTS - HQ422SS16 ( 011399 )
Project Tiltle
Modification of LP Separator Bridle Flushing System
Client
Al Khafji Joint Operations
Client Contact
Mohamd K. Alam
013 765 6726
Value "SAR"
324,375
Location
Khafji
Duration
25/6/2019
to 22/12/2020
Duration
Ongoing
EPC, MTD & BD - PROJECTS No. 19053592
Project Tiltle
Replacement of 42” Flare Line at GCs 03,04,06,07,08 and Drain Sump Vent Line at GCs 03,04,06,07,08 & 21 Flushing System
Client
KOC
Almeer Ref
CC-1178
Value In "DOLLAR"
6,290,000
Start Date
6/12/2019
Duration
8/29/2021
Discipline Covered
Mechanical
EPC, MTD & BD - PROJECTS No. 18052573
Project Tiltle
DCS Upgrate @ GCs. 1,3,4,6,7,8,19& 21 and EWDPs 1 & 2
Client
KOC/Emerson
Almeer Ref
CC-1174
Value In "DOLLAR"
14,556,452
Start Date
10/15/2018
Duration
4/1/2021
Discipline Covered
Instrumen
tation
EPC, MTD & BD - PROJECTS No. 1224962
Project Tiltle
DCS Upgrate @ GCs. 1,3,4,6,7,8,19& 21 and EWDPs 1 & 2
Client
KOC/SAIPEM
Almeer Ref
CC-1176
Value In "DOLLAR"
10,889,410
Start Date
6/1/2019
Duration
5/31/2020
Discipline Covered
Electrical & Instrumen
tation
EPC, MTD & BD - PROJECTS No. 14051259
Project Tiltle
Provision of Technical Staff for KOC Marine Maintenance services
Client
KOC
Almeer Ref
SC-2104
Value In "DOLLAR"
31,091,181
Start Date
11/1/2014
Duration
10/30/2019
Discipline Covered
Mechanical,Electrical & Instrumentation
EPC, MTD & BD - PROJECTS No. 14051353
Project Tiltle
Operation & Maintenance of Bulk Chemical Facilities and Effluent Water Disposal Plants in Company Areas
Client
KOC
Almeer Ref
SC-6100
Value In "DOLLAR"
29,510,921
Start Date
11/15/2014
Duration
11/14/2019
Discipline Covered
Mechanical,Electrical & Instrumentation
EPC, MTD & BD - PROJECTS No. 80000067
Project Tiltle
Electrical Manpower supply contract
Client
EQUATE
Our Ref
SC-2037
Value In "DOLLAR"
1,858,065
Start Date
12/1/2016
Duration
11/30/2019
Discipline Covered
Electrical & Instrumentation
EPC, MTD & BD - PROJECTS No. 4500003656
Project Tiltle
CP System Maintenance in Equate
Client
EQUATE
Our Ref
SC-2091
Value In "DOLLAR"
1,858,065
Start Date
11/7/2016
Duration
12/30/2021
Discipline Covered
Cathodic Protection
EPC, MTD & BD - PROJECTS No. ME/EW/MC/4582-2012/13
Project Tiltle
Annual Maintenance Works for Electrical at Shuwaikh Water Distillation Station
Client
MEW
Our Ref
SC-2099
Value In "DOLLAR"
9,060,419
Start Date
1/17/2013
Duration
30/06/2019
Discipline Covered
Electrical
EPC, MTD & BD - PROJECTS No.
Project Tiltle
Electrical & Instrument
Maintenance Services
Client
JO
Our Ref
SC-6101
Value In "DOLLAR"
47,424,594
Start Date
2/4/2015
Duration
2/3/2020
Discipline Covered
Electrical & Instrumentation
EPC, MTD & BD - PROJECTS No.15051363
Project Tiltle
Condition Monitoring & Preventive Maintenance Services of Production Facilties in SEK Areas.
Client
KOC
Our Ref
SC-6103
Value In "DOLLAR"
117,146,278
Start Date
12/1/2015
Duration
11/30/2020
Discipline Covered
Mechanical,Electrical,
Instrumentation
EPC, MTD & BD - PROJECTS No. 16052538
Project Tiltle
Comprehensive maintenance of Fire and Gas Detection system in North & West Kuwait Areas
Client
KOC
Our Ref
SC-6105
Value In "DOLLAR"
31,193,176
Start Date
11/14/2016
Duration
11/13/2021
Discipline Covered
Instrumentation/(F&G)
EPC, MTD & BD - PROJECTS No.18051967
Project Tiltle
Maintenance & training services for Daniel Metering Facilities
Client
KOC
Our Ref
SC-6109
Value In "DOLLAR"
5,329,019
Start Date
2/11/2018
Duration
2/11/2023
Discipline Covered
Instrumentation
EPC, MTD & BD - PROJECTS No.4500003911
Project Tiltle
Temporary Manpower
Client
Equate
Our Ref
SC-6106
Value In "DOLLAR"
Unit Rate
Start Date
4/1/2017
Duration
3/31/2022
Discipline Covered
MP Supply
EPC, MTD & BD - PROJECTS No. ME/MC/5248/2017/2018
Project Tiltle
Annual Maintenance Works for instrumentation & control systems at Alzour south power and water distillation station
Client
MEW
Our Ref
SC-6107
Value In "DOLLAR"
34,000,000
Start Date
12/5/2017
Duration
12/4/2022
Discipline Covered
Instrumentation
EPC, MTD & BD - PROJECTS No. 1128296
Project Tiltle
Subcontract Job # 1147126 Scope of Work #032192 Bottom Tank Cathodic Protectioon Works - Civil Activities
Client
Subcontract/Saipem
Almeer Ref
CC-1177
Value In "DOLLAR"
4,668,784
Start Date
12/5/2018
Duration
3/30/2020
Discipline Covered
E&I / CP / Civil
EPC, MTD & BD - PROJECTS No. 1147126 / 1128296
Project Tiltle
BOTTOM TANK CATHODIC PROTECTION WORKS FOR AL-ZOUR REFINERY PROJECT PACKAGE #4 (SAIPEM JOB REF: KW032192)
Client
KNPC/SAIPEM
Our Ref
1167
Value In "DOLLAR"
Start Date
2,488,498,774
12/1/2016
Duration
3/30/2020
Discipline Covered
Cathodic Protection / Streer Light
EPC, MTD & BD - PROJECTS No. SC6109/004/2018
Project Tiltle
UPGRADATION OF METERING SYSTEM -KHADMA AND LINE FILL METER
Client
KOC/ALMEER MAINTENANCE
Our Ref
1173
Value In "DOLLAR"
Start Date
548,387
2/24/2018
Duration
2/24/2023
Discipline Covered
Mechanical, Instrumentation and Electrical
EPC, MTD & BD - PROJECTS No. 13050755
Project Tiltle
Supply,Installation&Maintenance of scada system at North kuwait
Field Instrument / RTU panel /Scada for 157 ESP wells
Client
KOC/BAKERHUGHES
Our Ref
SCR-2015
Value In "DOLLAR"
2,264,516
Start Date
9/14/2014
Duration
3/17/2021
Discipline Covered
Discipline - SCADA Instrumentation
EPC, MTD & BD - PROJECTS No. 11050108
Project Tiltle
Scada/RTU infrastructure for 200 wells
Field Instrument / RTU panel /Scada for 200 ESP wells
Client
KOC/SCHLUMBERGER
Our Ref
SCR-2023
Value In "DOLLAR"
5,922,581
Start Date
3/18/2015
Duration
10/31/2020
Discipline Covered
Discipline - SCADA Instrumentation
EPC, MTD & BD - PROJECTS No. 80000061
Project Tiltle
Calibration of Tools
Client
Equate
Our Ref
SCR-2001
Value In "DOLLAR"
Unit Rate
Start Date
2/1/2016
Duration
1/31/2021
Discipline Covered
Valve Services
EPC, MTD & BD - PROJECTS No. 80000058
Project Tiltle
Valve Reconditioning
Client
Equate
Our Ref
SCR-2001
Value In "DOLLAR"
Unit Rate
Start Date
5/19/2016
Duration
1/1/2020
Discipline Covered
Valve Services
EPC, MTD & BD - PROJECTS No. 0-6798-Z-3170-001
Project Tiltle
E&I CONSTRUCTION WORKS AT MINA AL AHMADI REFINERY
Client
KNPC/SKEC
Our Ref
1161
Value In "DOLLAR"
12,345,342
Start Date
6/16/2015
Duration
7/31/2019
Discipline Covered
Electrical & Instrumentation
EPC, MTD & BD - PROJECTS No. 208-102
Project Tiltle
EPF 50 UPGRADE- CIVIL &PIPING WORKS
Client
KOC/GOFSCO
Our Ref
1170
Value In "DOLLAR"
8,276,146
Start Date
7/17/2017
Duration
6/30/2019
Discipline Covered
Civil & Piping
EPC, MTD & BD - PROJECTS No. 17051827
Project Tiltle
JURASSIC PRODUCTION FACILITIES OFF-PLOT WORKS AT NORTH KUWAIT AREAS PART B: INSTALLATION OF NEW LP LEAN GAS COMPRESSORS SYSTEM AND ASSOCIATED WORKS AT BOOSTER STATION BS-180 - ELECTRICAL & INSTRUMENTATION SUBCONTRACTOR WORKS
Client
KOC/CGC
Our Ref
1172
Value In "DOLLAR"
4,124,658
Start Date
3/20/2018
Duration
8/31/2019
Discipline Covered
Electrical & Instrumentation
EPC, MTD & BD - PROJECTS No.
Project Tiltle
EPF-50 Revamp – 210 MMSCFD Crude Section Works
Client
KOC/GOFSCO
Our Ref
SCR-2033
Value In "DOLLAR"
630,691,612.90
Start Date
11/14/2017
Duration
9/30/2019
Discipline Covered
Electrical & Instrumentation
EPC, MTD & BD - PROJECTS No.
Project Tiltle
Well Head Maintenance & Services for 70 Jurassic Wells in North Kuwait
Client
KOC/GOFSCO
Our Ref
SCR-2037
Value In "DOLLAR"
1,983,483,87
Start Date
5/1/2017
Duration
8/31/2019
Discipline Covered
SCADA - Instrumentation
EPC, MTD & BD - PROJECTS No.
Project Tiltle
Scope SCADA / RTU / Instrument for 22 ESP Wells
Client
KOC/BORETS
Our Ref
SCR-2040
Value In "DOLLAR"
645.16
Start Date
9/20/2018
Duration
3/30/2020
Discipline Covered
SCADA - Instrumentation
EPC, MTD & BD - PROJECTS No. D-2019-594
Project Tiltle
Construction of Transmission pipeline
Client
General Directorate of water Basra water Improvement Project
Our Ref
SCR-2040
Value In "DOLLAR"
126,462,283.87
Start Date
2019
Duration
2021
Discipline Covered
Civil & Piping
COMPLETED PROJECTS
COMPLETED PROJECTS No.6510888788
Project Tiltle
LED Flood Lights Installation
at LIP Dhahran
Client
Saudi
Aramco
Client Contact
Abdul Azeez
Value In "DOLLAR"
58,667
Work Specific Location
Dhahran
Duration
24/09/2018 to 23/12/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.6510889961
Project Tiltle
Installation of Redundant Power Feeder & AC system
Client
Saudi
Aramco
Client Contact
Abdul Azeez
Value In "DOLLAR"
56,000
Work Specific Location
Dhahran
Duration
26/09/2018 to 27/12/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.6600028166
Project Tiltle
Base Crew Services NGPD
Providing Skilled Manpower for Maintenance Activities of all Plants related to NGPD and SWID
Client
Saudi
Aramco
Client Contact
Mohammed Sager Tel. 5765337
Value In "DOLLAR"
5,760,000
Work Specific Location
North Gawar Producing Abqaiq
Duration
15/09/2013 to 31/07/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.6510693609
Project Tiltle
WCM & BS&W Analyzers Preventive Maintenance & Repair
Client
Saudi
Aramco
Client Contact
Ahmed Shagal
Value In "DOLLAR"
4,986,667
Work Specific Location
S. Ghawar Producing
Duration
30/11/2014 to 20/11/2017
Discipline Covered
Completed
COMPLETED PROJECTS No.6510691140
Project Tiltle
Replace Communication Shelter at Hawtah with ATS, MTS & UGDT
Client
Saudi
Aramco
Client Contact
Dalal Al thukair
Value In "DOLLAR"
194,667
Work Specific Location
Hawtah
Duration
10/07/2018 to 04/07/2019
Discipline Covered
Completed
COMPLETED PROJECTS No.6510870487
Project Tiltle
Replacing Remote Control System for Berth 52 Loading Arms - Offshore
Client
Saudi
Aramco
Client Contact
Munner S. Al Dahi
Value In "DOLLAR"
48,469
Work Specific Location
Juaymah
Duration
01/04/2018 to 29/12/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.3000809606-2
Project Tiltle
Perform Calibration and Certification of Beamex Equipment
Client
Saudi
Aramco
Client Contact
Saad Ali Al-Qahtani
013 576-5004
Value In "DOLLAR"
5,653
Work Specific Location
Shedgum Gas Plant
Duration
17/10/2018 to 16/11/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.4300043641
Project Tiltle
REPLACEMENT OF PIPING FOR SAFCO-III UTILITIES ACID DOSING PUMPS
Client
Saudi
Aramco
Client Contact
Saqib Nazir
Tel. 13-342 2963
Value In "DOLLAR"
49,333
Work Specific Location
Safco, Jubail
Duration
01/08/2016 to
10/11/2016
Discipline Covered
Completed
COMPLETED PROJECTS No.6510870420
Project Tiltle
COMMISSION AND RECOMMISSION TWO NOS 881 NSL SULFUR PIT ANALYZER
Client
Saudi
Aramco
Client Contact
ABDUL SATTAM BENSAAD
+966-13-5774653
Value In "DOLLAR"
19,200
Work Specific Location
Shedgum
Duration
10/05/2018 to 11/07/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.4300187731
Project Tiltle
SUPPLY AND LAY LV CABLE FOR PH-4 LOX BACKUP PUMP
Client
Saudi
Aramco
Client Contact
KAZEEM SALEH
+966 13 350 6105
Value In "DOLLAR"
45,333
Work Specific Location
Jubail
Duration
2/05/2018 TO 20/07/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.6510867754
Project Tiltle
Installation of Gravity Sewer Lavel transmitter at Hawtah FCC
Client
Saudi
Aramco
Client Contact
JT George
Value In "DOLLAR"
119,467
Work Specific Location
Hawtah
Duration
5/6/2018 to 9/30/2018
Discipline Covered
Completed
COMPLETED PROJECTS No.6510642432
Project Tiltle
Inspection, Testing & Assessment of all Equipment and Auxillaries related to Power Distribution System, Cathodic Protection System and Emergency Diesel Generators (EDG)
Client
Saudi
Aramco
Client Contact
Value In "DOLLAR"
894,733
Work Specific Location
Yanbu
Duration
16/02/2014 to 01/05/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.PO 1617-1781
Project Tiltle
Removal of valves from site, service, repair, overhaul, testing and reinstallation of 198 Nos. of valves types includes (blow down valves types, control valves, shutdown valves, Manual Isolation valves, MOV etc) Sizes (1"till32")
Client
Al Khafji Operation
Client Contact
Value In "DOLLAR"
853,333
Work Specific Location
KJO Gas Plant
Duration
21/02/2013 to 15/04/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.3000517195
Project Tiltle
Valve cleaning, greasing, sealing and repair at valves at QSWIP plant
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
604,728
Work Specific Location
Qurrayah
Duration
15/12/2013 to 15/12/2015
Discipline Covered
Completed
COMPLETED PROJECTS No.PPO dtd 11/20/2013
Project Tiltle
Replacement of Insulation and Water Proofing System of Laboratory Building, CCR and Admin of Qurrayah Sea Water Plant
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
293,333
Work Specific Location
Qurrayah
Duration
15/01/2014 to 01/06/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.6510591760
Project Tiltle
Maintenance of Process Analyzers and Gas Chromotographs and Commissioning at AMETEK Analyzers at Haradh Gas Plant Sulphur Unit
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
188,000
Work Specific Location
Haradh Gas Plant
Duration
16/01/2014 to 14/07/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.PO#1788
Project Tiltle
Repair, maintenance, overhaul and testing of various types of Valves including removal and reisntallation. Servicingf and overhausl of Chemical dosing/metering pumps of Water Plant at KJO
Client
Al-Khafji Operation
Client Contact
Value In "DOLLAR"
170,667
Work Specific Location
Khafji
Duration
15/06/2013 to 31/07/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.6510638423
Project Tiltle
Maintenance of Process Analyzers and Gas Chromatograph at Haradh Gas Plant
Client
Al-Khafji Operation
Client Contact
Ahmed Al-Ghamdi
Value In "DOLLAR"
148,096
Work Specific Location
Haradh Gas Plant
Duration
15/06/2013 to 16/12/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.6510647908
Project Tiltle
Provide Hydraulic Torquing Services for NGID total Shutdown
Client
Al-Khafji Operation
Client Contact
Ahmed Al-Ghamdi
Value In "DOLLAR"
136,296
Work Specific Location
Various location
Duration
10/03/2014 to 10/04/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.PO AL&P/FM/F17664
Project Tiltle
Structural Fabrication Works
Client
Saudi Aramco
Client Contact
Ahmed Al-Ghamdi
Value In "DOLLAR"
114,667
Work Specific Location
Jubail
Duration
05/08/2012 to 31/12/2012
Discipline Covered
Completed
COMPLETED PROJECTS No. PO # 1671
Project Tiltle
Calibration and ReCommissioning of analyzers at KJO Gas Plant
Client
Al-Khafji Joint operations
Client Contact
Value In "DOLLAR"
108,000
Work Specific Location
Khafji
Duration
15/09/2013 to 15/05/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.6510768108
Project Tiltle
Offline Valves Repair and Greasing at SHGOSP - 1&5
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
88,600
Work Specific Location
Shedgum
Duration
05/01/2016 to 05/05/2016
Discipline Covered
Completed
COMPLETED PROJECTS No.6510668806
Project Tiltle
ABNWIP/Replace the roofing insulation of Switchgear room
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
78,000
Work Specific Location
Abqaiq
Duration
13/07/2014 to 11/10/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.3000481845
Project Tiltle
Replacement of Roofing Insulation and Waterproofing for the Roof of Desalter Switchgear Building
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
74,667
Work Specific Location
Abqaiq
Duration
01/11/2011/ to 30/11/2012
Discipline Covered
Completed
COMPLETED PROJECTS No.PO 01617-RO1
Project Tiltle
Calibration of Rolls Royce Turbine instrument at Gas Plant of KJO
Client
Al-Khaji Joint Operation
Client Contact
Value In "DOLLAR"
69,333
Work Specific Location
Hawiyah NGL
Duration
21/02/2013 to 31/03/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.Saudi Aramco
Project Tiltle
Repair of Pressure Control Valves
Client
Saudi Aramco
Client Contact
Hamoud Al-Hajeri Tel. 05722561
Value In "DOLLAR"
69,333
Work Specific Location
ABGOSP-2
Duration
20/04/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.Saudi Aramco
Project Tiltle
Well injection Pump & motor Lube Oil System Troubleshooting, Repair & Start up at Abqaiq PCR-6
Client
Saudi Aramco
Client Contact
Hamoud Al-Hajeri Tel. 05722561
Value In "DOLLAR"
58,667
Work Specific Location
ABQ PCR -6
Duration
17/10/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.Saudi Aramco
Project Tiltle
Valve Troubleshooting, Repair & Testing at Abqaiq NQIP
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
50,667
Work Specific Location
Abqaiq NWIP
Duration
14/09/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.6600028166
Project Tiltle
Provide Technicians for CPU, SH
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
49,190
Work Specific Location
Qurrayah
Duration
18/05/2014 to 18/11/2014
Discipline Covered
Completed
COMPLETED PROJECTS No.Saudi Aramco
Project Tiltle
Valve Troubleshooting, Repair & Testing at Abqaiq NQIP
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
48,000
Work Specific Location
Abqaiq SWIP
Duration
18/09/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.PO 480000698
Project Tiltle
Fabrication of access ladders
and w/safety cage
Client
Samsung
Client Contact
Value In "DOLLAR"
40,000
Work Specific Location
Duration
24/02/2013 to 26/03/2013
Discipline Covered
Completed
COMPLETED PROJECTS No. 30000486620
Project Tiltle
Calibration of Inspectuon Unit devices at HGPD
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
40,000
Work Specific Location
Hawiyah NGL
Duration
05/06/2013 to 21/08/2013
Discipline Covered
Completed
COMPLETED PROJECTS No.Saudi Aramco
Project Tiltle
Flanged Joint Leak Repair at Abqaiq NWIP
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
32,000
Work Specific Location
Abqaiq SWIP
Duration
22/10/2013
Discipline Covered
Completed
COMPLETED PROJECTS No. JL010503 MIS ARABIA
Project Tiltle
Fabrication of transportation Saddles
Client
MIS arabia
Client Contact
Value In "DOLLAR"
29,333
Work Specific Location
Duration
30/07/2013 to 30/08/2013
Discipline Covered
Completed
COMPLETED PROJECTS No. Al Bawardi Steel
Project Tiltle
Fabrication of Pipe Handrails
Client
Al Bawardi Steel Industrial
Client Contact
Value In "DOLLAR"
22,667
Work Specific Location
Duration
05/11/2013 to 25/11/2013
Discipline Covered
Completed
COMPLETED PROJECTS No. 9510553492
Project Tiltle
Calibration of PMI, UT Machine & UT Gage @ HNGL
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
21,333
Work Specific Location
Hawiyah NGL
Duration
15/09/2012 to 24/10/2012
Discipline Covered
Completed
COMPLETED PROJECTS / Saudi Aramco
Project Tiltle
Pump Alignment Job in AWWSU, PR4
Client
Saudi Aramco
Client Contact
Value In "DOLLAR"
18,400
Work Specific Location
AWWSU
PR-4
Duration
Discipline Covered
Completed
COMPLETED PROJECTS / 6600033834
Project Tiltle
Upgrade Control System at Uthmaniyah and Hawiyah GOSPs
Client
Saudi Aramco
Client Contact
Ahmad Saleh
+96655 455 2836
Value In "DOLLAR"
36,528,000
Work Specific Location
Uthmaniyah and Hawiyah
Duration
30/11/2014 to 30/06/2019
Discipline Covered
Completed
COMPLETED PROJECTS No.4800000172
Project Tiltle
Fabrication of Channel base plates for Qurayyah IPP 380/230kV substation
Client
Samsung
Client Contact
Value In "DOLLAR"
16,000
Work Specific Location
Workshop
Duration
01/10/2011 to 05/11/2012
Discipline Covered
Completed
COMPLETED PROJECTS No. 1128296
Project Tiltle
UNIT # 77, ELECTRICAL WORKS FOR NEW REFINERY PROJECT PACKAGE #4 (SAIPEM JOB REF: KW032192)
Client
KIPIC/MEW/SAIPEM
Our Ref
1167
Value In "DOLLAR"
1,826,508
Start Date
11/15/2016
Duration
10/30/2018
Discipline Covered
Electrical
COMPLETED PROJECTS No. L&T/KUW/0115/SC/AG/0019
Project Tiltle
ELECTRICAL & INSTRUMENTATION SHUTDOWN WORKS FOR REPLACEMENT OF OLD & OBSOLETE SUBSTATION M20 AT MAA REFINERY PROJECT
Client
KNPC/L&T
Our Ref
1175
Value In "DOLLAR"
344,028
Start Date
5/1/2018
Duration
12/31/2018
Discipline Covered
Electrical
COMPLETED PROJECTS
Project Tiltle
ELECTRICAL & INSTRUMENTATION SHUTDOWN WORKS FOR REPLACEMENT OF OLD & OBSOLETE SUBSTATION M20 AT MAA REFINERY PROJECT
Client
EK2
Our Ref
SC-6108
Value In "DOLLAR"
14,494,149
Start Date
1/1/2018
Duration
12/30/2018
Discipline Covered
Mechanical,Electrical,
Instrumentation
COMPLETED PROJECTS No. 4500002586
Project Tiltle
Bolt Torqing & tensioning and other services
Client
EQUATE
Our Ref
SC-2101
Value In "DOLLAR"
1,612,903
Start Date
7/20/2013
Duration
10/31/2018
Discipline Covered
Mechanical
COMPLETED PROJECTS No. 4500003546
Project Tiltle
Control Valve Diagnostics Services
Client
EQUATE
Our Ref
SCR-2001
Value In "DOLLAR"
Unit Rate
Start Date
4/17/2016
Duration
4/18/2019
Discipline Covered
Discipline - Valve Services
COMPLETED PROJECTS No.
Project Tiltle
Supply & Install Transformer
Client
KOC
Our Ref
SCR-2026
Value In "DOLLAR"
1,001,206
Start Date
6/15/2016
Duration
7/7/2018
Discipline Covered
Electrical & Civil
COMPLETED PROJECTS No. SAC/OED-MRN/541
Project Tiltle
Site survey,Detailed Engineering, Supply,Software with Licenses,Site Services,Integration,SAT,FAT,Testing,Pre-commissioning,Commissioning and training for telemetry system works and DCS System
Client
SAC/HEISCO
Our Ref
SCR-2029
Value In "DOLLAR"
1,735,310
Start Date
4/19/2017
Duration
5/30/2018
Discipline Covered
Telemetry & Instrumentation
COMPLETED PROJECTS No.
Project Tiltle
JPF 20 WELL SCADA projects
Client
GOFSCO
Our Ref
SCR-2032
Value In "DOLLAR"
2,570,806
Start Date
11/1/2017
Duration
5/30/2018
Discipline Covered
SCADA Instrumentation
COMPLETED PROJECTS No. 14050922
Project Tiltle
Supplying, Installation & Commissioning of SCADA system for 127 wells at SEK
(Producing ESP and Water Injection)
Client
KOC/WEATHERFORD
Our Ref
SCR-2034
Value In "DOLLAR"
4,887,584
Start Date
7/1/2018
Duration
12/31/2018
Discipline Covered
SCADA Instrumentation
COMPLETED PROJECTS No.
Project Tiltle
Construction, PRE-Commissioning works of 20 wells
Client
GOFSCO
Our Ref
SCR 2035
Value In "DOLLAR"
3,151,452
Start Date
4/1/2018
Duration
9/30/2018
Discipline Covered
SCADA Instrumentation
COMPLETED PROJECTS No.
Project Tiltle
EPF-50 Revamp-210MMSSCFD crude section works
Client
GOFSCO
Our Ref
SCR 2036
Value In "DOLLAR"
501,613
Start Date
3/1/2018
Duration
7/31/2018
Discipline Covered
Civil works
COMPLETED PROJECTS No.
Project Tiltle
EPF-50 Revamp-210MMSSCFD crude section works
Client
SCHLUMBERGER
Our Ref
SCR 2028
Value In "DOLLAR"
2,903,139
Start Date
6/1/2018
Duration
9/30/2018
Discipline Covered
E&I
COMPLETED PROJECTS No. AC/OED-MRN/541
Project Tiltle
SCADA Civil & Electrical work
Client
WEATHERFORD
Our Ref
SCR 2039
Value In "DOLLAR"
5,122,581
Start Date
7/1/2018
Duration
12/31/2018
Discipline Covered
SCADA Instrumentation
COMPLETED PROJECTS No.
Project Tiltle
Maintenance of power plant
Client
GE SUBITA
Our Ref
SCR 3001
Value In "DOLLAR"
742,700
Start Date
1/1/2018
Duration
12/31/2018
Discipline Covered
Electrical
COMPLETED PROJECTS No. 15051408
Project Tiltle
Maintenance of SCADA system for KwIDF Sabriyah 49 Wells Kuwait Oil Field
Client
KOC/HALLIBURTON
Our Ref
SCR 3015
Value In "DOLLAR"
6,216,774
Start Date
6/20/2011
Duration
12/31/2018
Discipline Covered
Instrumentation SCADA Maninetanance
COMPLETED PROJECTS No. 12050743
Project Tiltle
Installation Commissioning & Maintenance of WHAP Wellhead Automation for 30 Jurassic Wells at North Kuwat
Client
GOFSCO
Our Ref
SCR 2030
Value In "DOLLAR"
3,983,332
Start Date
6/1/2017
Duration
12/31/2018
Discipline Covered
COMPLETED PROJECTS No. L&T/KUW/0115/SC/AG/0014
Project Tiltle
REPLACEMENT OF OLD & OBSOLETE SUBSTATION M20 AT MAA REFINERY PROJECT- E&I WORKS
Client
KNPC/L&T
Our Ref
1161 A
Value In "DOLLAR"
3,983,332
Start Date
3/1/2017
Duration
6/30/2018
Discipline Covered
Electrical & Instrumentation
COMPLETED PROJECTS No. 14051100
Project Tiltle
Replacement of HIC Affected non nace Seprators and Gas Scrubbers at
SEK GC'9,10,20 & 22
Client
KOC/MECC
Our Ref
SC-2024
Value In "DOLLAR"
250,874
Start Date
1/1/2016
Duration
1/1/2018
Discipline Covered
E&I
COMPLETED PROJECTS No.
Project Tiltle
EPF 10 Upgradation work for existing facility
Client
KOC / GOFSCO
Our Ref
CC1171
Value In "DOLLAR"
6,191,490
Start Date
11/30/2017
Duration
4/30/2018
Discipline Covered
Civil, Piping & E&I
COMPLETED PROJECTS No.
Project Tiltle
Modification work for existing facility 208-101-Civil & Piping
Client
KOC / GOFSCO
Our Ref
CC1169
Value In "DOLLAR"
16,177,587
Start Date
5/1/2017
Duration
10/12/2017
Discipline Covered
Civil & Piping
COMPLETED PROJECTS No.
Project Tiltle
EPF-50 Upgrade to 2100 MMSCFD-Piping & Civil works
Client
KOC / GOFSCO
Our Ref
CC1166
Value In "DOLLAR"
6,892,427
Start Date
10/15/2015
Duration
4/30/2017
Discipline Covered
Civil & Piping
COMPLETED PROJECTS No.MEW/MC/4998/2015-2016
Project Tiltle
Supply and install lighting protection system for transformer and gas scrubber area at doha east power & water distillation Station
Client
MEW
Our Ref
CC1163
Value In "DOLLAR"
80,000
Start Date
10/7/2015
Duration
10/7/2017
Discipline Covered
Electrical
COMPLETED PROJECTS No
Project Tiltle
Miscellaneous Works(Instrumentation, Electrical, Mechanical and Civil Works) for new Dry cude Tank at GC-01 Excluding Fire Proofing and Epoxy Painting Activities.
Client
KOC/Gulf International
Our Ref
BD 4089
Value In "DOLLAR"
1686,74
Start Date
12/6/2015
Duration
3/6/2017
Discipline Covered
Mechanical,Electrical,Instrumentation & Civil works
COMPLETED PROJECTS No. 10031-2401
Project Tiltle
FIE Inspection services and support for Al-Zour Refinery Project
Client
KIPIC / Technicas Reunidas
Our Ref
CC 1164
Value In "DOLLAR"
1,345,558
Start Date
11/5/2015
Duration
4/23/2018
Discipline Covered
Inspection
COMPLETED PROJECTS No. 019181D-OP03001
Project Tiltle
New booster station BS -132 AND Enhancement to BS-131, North Kuwait Project-Portion-2 E&I Works
Client
KOC/SKE & C
Our Ref
CC 1160
Value In "DOLLAR"
1,935,484
Start Date
4/21/2014
Duration
4/30/2015
Discipline Covered
E&I
COMPLETED PROJECTS No. 9600039591
Project Tiltle
Sabriyah KWIDF Project, NK Kuwait Oil Company (Engineering & procurement for 18 wells)
Client
KOC/HALLIBURTON
Our Ref
CC 1156
Value In "DOLLAR"
3,417,133
Start Date
6/28/2011
Duration
4/30/2015
Discipline Covered
E&I
COMPLETED PROJECTS No. 12050869
Project Tiltle
Supply,Installation and Commissioning support of replacement of DCS,ESD,,F&G and HIPPS systems at KOC-NK EPF 50
Client
KOC/MECC
Our Ref
BD/4009/15
Value In "DOLLAR"
2,978,871
Start Date
6/4/2015
Duration
4/26/2016
Discipline Covered
E&I
COMPLETED PROJECTS No.
Project Tiltle
Foundation Works
Client
KOC/GOFSCO
Our Ref
1162
Value In "DOLLAR"
629,032.26
Start Date
10/20/2015
Duration
1/20/2016
Discipline Covered
CIVIL
COMPLETED PROJECTS No. 14051353
Project Tiltle
Flow metering system and well test system
Client
KOC
Our Ref
BD 3156/SCR 2020
Value In "DOLLAR"
217,474
Start Date
9/28/2014
Duration
12/16/2015
Discipline Covered
INSTRUMENTATION
COMPLETED PROJECTS No. AA/23/1014
Project Tiltle
Ware house management system
Client
PIC
Our Ref
BD 3151/2014
Value In "DOLLAR"
196,665
Start Date
12/12/2014
Duration
12/12/2015
Discipline Covered
EPC
COMPLETED PROJECTS No.12050653
Project Tiltle
UPGRADING OF DISTRIBUTED CONTROL SYSTEM & ASSOCIATED WORKS IN GC-17, 27 & 28
Client
KOC
Our Ref
CC1159
Value In "DOLLAR"
11692390
Start Date
8/15/2012
Duration
3/6/2014
Discipline Covered
EPC
COMPLETED PROJECTS No.MNS/08/2013
Project Tiltle
DESIGN,ENGINEERING,
PRECUREMENT,CONSTRUCTION AND COMMISSIONINGOF INSTRUMENTATION REVAMP OF INSTRUMENTATION FOR AMMONIA III COMPRESSOR AT PIC PLANT B
Client
PIC
Our Ref
SCR-2014
Value In "DOLLAR"
2,191,935
Start Date
5/12/2012
Duration
12/13/2014
Discipline Covered
EPC
COMPLETED PROJECTS No. ACT-4025/2K7
Project Tiltle
Installation of new air assisted flare stacks at gc-16, 17, 27 & 28
Client
KOC
Our Ref
SC-2081
Value In "DOLLAR"
1,596,774
Start Date
2007-2010
Duration
2007-2010
Discipline Covered
Instrumentation
COMPLETED PROJECTS No. SC/EMD/KOC-32861/2008/002
Project Tiltle
Improvement to Header ESD System in 6 GCs
Client
KOC
Our Ref
SC-2084
Value In "DOLLAR"
475,806
Start Date
2008-2010
Duration
2008-2010
Discipline Covered
Instrumentation
COMPLETED PROJECTS No.
Project Tiltle
Supply & Modification of RS3 DCS works at KOC GC's 1,2,4,6,7,19 & 21
Client
KOC
Our Ref
SC-2063
Value In "DOLLAR"
1,147,990
Start Date
2006-2010
Duration
2006-2010
Discipline Covered
Instrumentation
COMPLETED PROJECTS No. LPG/OPS-09/2007
Project Tiltle
Re-Conditioning of 12KG LPG Cylinders
Client
KOTC
Our Ref
SC-2056
Value In "DOLLAR"
2,608,065
Start Date
2006-2010
Duration
2006-2010
Discipline Covered
Maintenance
COMPLETED PROJECTS No. 28916
Project Tiltle
50 MBOPD EPF-2 FOR NORTH KUWAIT JURASSIC PRODUCTION
Client
KOC
Our Ref
SC-2090
Value In "DOLLAR"
2,197,368
Start Date
1/3/2008
Duration
2/28/2009
Discipline Covered
EPC
COMPLETED PROJECTS No. 016432-P 8101
Project Tiltle
GC-27 New Desalter & Light Crude train modifications and capacity expansion for Effluent Water separation (RS3 DCS system modification works)
Client
KOC
Our Ref
SC-2058
Value In "DOLLAR"
1,274,194
Start Date
15/07/2005
Duration
10/31/2007
Discipline Covered
Instrumentation
COMPLETED PROJECTS No. 0/2823/05
Project Tiltle
Supply, Installation, Testing, Training & Commissioning of complete PLC and DCS System at MAA Refinery for KNPC
Client
Nouri IND./KNPC - MAA
Our Ref
SC-2053
Value In "DOLLAR"
458,065
Start Date
7/1/2005
Duration
4/30/2007
Discipline Covered
Instrumentation
COMPLETED PROJECTS No. 46096
Project Tiltle
UPGRADE OF CHEMICAL INJECTION & MONITORING CAPABILITY AT WEST KUWAIT FACILITIES
Client
KOC
Our Ref
CC-1151
Value In "DOLLAR"
25,604,977,42
Start Date
2/1/2011
Duration
3/31/2015
Discipline Covered
EPC
COMPLETED PROJECTS No. 46762
Project Tiltle
FIRST POTABLE WATER PIPELINE NETWORK FOR WEST KUWAIT [WK FACILITIES]
Client
KOC
Our Ref
CC-1153
Value In "DOLLAR"
7,712,903
Start Date
3/20/2011
Duration
9/10/2013
Discipline Covered
EPC
COMPLETED PROJECTS No. CB/CSPD/2004
Project Tiltle
Upgradation of Obsolete Fire Detection, Alarm and Suppression systems at KNPC sites including the phase out of Halon system (KNPC MAA Refinery)
Client
KNPC/HANWA
Our Ref
CC-1158
Value In "DOLLAR"
21,058,065
Start Date
6/1/2012
Duration
10/31/2013
Discipline Covered
Construction
COMPLETED PROJECTS No. CA/PD/3570
Project Tiltle
Engineering, Procurement & Construction Of Modernization Of Obsolete Instrumentation Project(Moip) MAA Refinery
Client
KNPC
Our Ref
CC-1140
Value In "DOLLAR"
130,904,226
Start Date
6/10/2006
Duration
12/31/2012
Discipline Covered
LV Electrical & Instrumentation
COMPLETED PROJECTS No. 43629
Project Tiltle
Installation of Engine Management Retrofits & Associated works
Client
KOC
Our Ref
CC-1150
Value In "DOLLAR"
1,342,810
Start Date
2010-2011
Duration
2010-2011
Discipline Covered
EPC
COMPLETED PROJECTS No. MPA No: 9600032152 [KOC CONT NO.41407]
Project Tiltle
SABRIYAH KWIDF PROJECT, NK
Client
KOC / HALLIBURTON
Our Ref
CC-1152
Value In "DOLLAR"
5,925,097
Start Date
7/20/2010
Duration
7/19/2011
Discipline Covered
EPC
COMPLETED PROJECTS No. 37195
Project Tiltle
Gas Sweetening Facility West Kuwait
Client
KOC/SAFWAN
Our Ref
SCR-2009/005/10
Value In "DOLLAR"
574,194
Start Date
2/4/2010
Duration
7/30/2010
Discipline Covered
E & I
COMPLETED PROJECTS No. 35468
Project Tiltle
Replacement Of 18” Crude Export Line From GC-20 UP To North Tank Farm
Client
KOC
Our Ref
CC-1146
Value In "DOLLAR"
3,618,300
Start Date
1/20/2008
Duration
2/13/2010
Discipline Covered
LV Electrical
COMPLETED PROJECTS No. 36403
Project Tiltle
Upgrading/Modification for Tankgauge, Injection Pump Sea Water Drainage System at MWIP - West Kuwait
Client
KOC
Our Ref
CC-1148
Value In "DOLLAR"
10,685,613
Start Date
4/7/2008
Duration
5/2/2010
Discipline Covered
LV Electrical
COMPLETED PROJECTS No. 38067
Project Tiltle
Power Diversion and Fire Protection Works in SEK
Client
KOC
Our Ref
CC-1149
Value In "DOLLAR"
10,233,387
Start Date
10/5/2008
Duration
12/12/2010
Discipline Covered
LV Electrical
COMPLETED PROJECTS No. 29152
Project Tiltle
Corrosion and Scale Monitoring & Inhibitor injection package for SEK (14 GC's)
Client
KOC
Our Ref
CC-1139
Value In "DOLLAR"
41,038,470
Start Date
8/15/2006
Duration
11/17/2010
Discipline Covered
LV Electrical
COMPLETED PROJECTS No. CB/1221
Project Tiltle
Replacement / up-gradation of nuclear level instruments in MAB-refinery unit-20
Client
KNPC
Our Ref
CC-1147
Value In "DOLLAR"
1,608,387
Start Date
1/1/2008
Duration
6/30/2009
Discipline Covered
EPC
COMPLETED PROJECTS No. CB1189
Project Tiltle
Replacement/Upgrading of Programmable Logic Controllers in Mina Abdullah Refinery
Client
KNPC-MAB
Our Ref
CC-1141
Value In "DOLLAR"
2,161,129
Start Date
2006-2008
Duration
2006-2008
Discipline Covered
Instrumentation
COMPLETED PROJECTS No. CS/PD/1805
Project Tiltle
Fire Detection System for Critical Pumps, Compressors & Lube Oil / Seal Oil Consoles at KNPC Shuaiba Refinery
Client
KNPC - Shuaiba
Our Ref
CC-1142
Value In "DOLLAR"
2,161,129
Start Date
2006-2008
(13 Months)
Duration
2006-2008
(13 Months)
Discipline Covered
LV Electrical, Instrumentation & Civil
COMPLETED PROJECTS No. UM2/908
Project Tiltle
OL2K Utilities - Mechanical 2 Project
Client
CCC
Our Ref
CC-1143
Value In "DOLLAR"
2,193,548
Start Date
2007-2008
(8 Months)
Duration
2007-2008
(8 Months)
Discipline Covered
Mechanical
COMPLETED PROJECTS No.KARO/1/2005
Project Tiltle
Electrical and Building Electrical Construction Wroks for KPPC Aromatics Complex Project in Shuaiba.
Client
SK Engineering/KPPC
Our Ref
CC-1144
Value In "DOLLAR"
3,410,116
Start Date
7/28/2007
Duration
2/28/2008
Discipline Covered
MV & LV Electrical
COMPLETED PROJECTS No.27070
Project Tiltle
New 52" LP and 42" HP Fuel Gas Lines from Shuaiba M/F (M/F SH01) to M/F "X" in Burgan
Client
KOC
Our Ref
CC-1137
Value In "DOLLAR"
31,100,323
Start Date
2005-2008
Duration
2005-2008
Discipline Covered
Instrumentation
Electrical
COMPLETED PROJECTS No. CB/1183
Project Tiltle
24" Strategic Crude Oil Supply Line
Client
KNPC - Mina Abdulla
Our Ref
CC-1135
Value In "DOLLAR"
714,484
Start Date
2005-2006
(15 Months)
Duration
2005-2006
(15 Months)
Discipline Covered
Mechanical
COMPLETED PROJECTS No. CS/PD/1756
Project Tiltle
Provision of ROIV's and Upgrade of Safety Interlock in process units.
Client
KNPC - SHUAIBA
Our Ref
CC-1136
Value In "DOLLAR"
7,169,326
Start Date
2005-2006
(15 Months)
Duration
2005-2006
(15 Months)
Discipline Covered
Mechancial
Electrical
COMPLETED PROJECTS No. 4500000623
Project Tiltle
Construction, Modification, Material supply, Manpower, Equipment, Commissioning & Start-up activities for Ethylene Glycol and Utilities Unit in Equate.
Client
Equate
Our Ref
CC-1138
Value In "DOLLAR"
1,598,490
Start Date
2005-2006
(6Months)
Duration
2005-2006
(6Months)
Discipline Covered
Instrumentation
Electrical
COMPLETED PROJECTS No. 23970
Project Tiltle
Replacement of fire water pumps & prime movers at GC-16,17 & BS-170 in West Kuwait
Client
KOC
Our Ref
CC-1134
Value In "DOLLAR"
4,947,790
Start Date
2004-2006
(18Months)
Duration
2004-2006
(18Months)
Discipline Covered
LV Electrical
COMPLETED PROJECTS No. 22473/ CC-1133
Project Tiltle
Debottle Necking of GC-276GC-28
Client
KOC
Our Ref
CC-1134
Value In "DOLLAR"
4,947,790
Start Date
2004-2005
(16Months)
Duration
2004-2005
(16Months)
Discipline Covered
Mechanical
Instrumentation
COMPLETED PROJECTS No. 20523
Project Tiltle
Brackish Water Pipeline Network & System Upgrades for South East Kuwait Areas
Client
KOC
Our Ref
CC-1130
Value In "DOLLAR"
3,280,645
Start Date
2004-2005
Duration
2004-2005
Discipline Covered
Electrical, Civil, Instrumentation
Mechanical
COMPLETED PROJECTS No.20831
Project Tiltle
Installation of new closed drain and Effluent water system at GC-15
Client
KOC
Our Ref
CC-1132
Value In "DOLLAR"
6,850,161
Start Date
2004-2005
(12Months)
Duration
2004-2005
(12Months)
Discipline Covered
Civil
Mechancial
COMPLETED PROJECTS No.19473
Project Tiltle
Construction of New B-2 & A-142 Substation Load Distribution, South East Kuwait.
Client
KOC
Our Ref
CC-1129
Value In "DOLLAR"
5,668,116
Start Date
2003-2005
(16Months)
Duration
2003-2005
(16Months)
Discipline Covered
Civil
Electrical
COMPLETED PROJECTS No. CA/3508
Project Tiltle
Replacement of Obsolete Analyzers in Units 61/48/49/51/52/91 & 92 in Mina Al Ahmadi refinery.
Client
KNPC/MAA
Our Ref
CC-1131
Value In "DOLLAR"
926,823
Start Date
2004-2004
(12Months)
Duration
2004-2004
(12Months)
Discipline Covered
Electrical
Instrumentation
COMPLETED PROJECTS No. :17767
Project Tiltle
Detailed Engineering, Procurement, Supply and Installation of Non-Smoke Igniter in Several Gathering Centers of Kuwait Oil Company (Phase II), including all the related works in the disciplines of Civil, Electrical & Instrumentation.
Client
KOC
Our Ref
CC-1128
Value In "DOLLAR"
6,975,306
Start Date
2004-2004
Duration
2004-2004
Discipline Covered
Civil, Electrical
Instrumentation
SCROLL
CONTACT
PROJECTS
SERVICE
COMPANY
HOME
COMPANY
SERVICES & FACILITIES
ENGINEERING
CALIBRATION
SYSTEMS INTEGRATION
VALVE MAINTENANCE &TESTING
FABRICATION WORKSHOP